Transformer sizing is a balance between two failure modes. Undersize the unit and it runs hot, ages prematurely and limits future expansion. Oversize it and you pay for capacity that never gets used, while no-load losses run continuously for the whole service life regardless of how lightly the transformer is loaded.
This page sets out a method for arriving at the right rating, with the factors that most often get overlooked.
The Method in Five Steps
Step 1 — Connected Load
List every load that will be supplied and sum the ratings. Motors, lighting, HVAC, process equipment, socket outlets, standby systems. This figure is almost always considerably higher than the load the transformer will actually see, but it is the starting point.
Step 2 — Demand and Diversity
Not everything runs at once, and what does run rarely runs at full rating. Two separate factors account for this:
Typical demand factors by installation type:
Step 3 — Converting kW to kVA
Transformers are rated in apparent power because their thermal limit is set by current, which flows regardless of the power factor of the load.
The power factor makes a substantial difference to the required rating:
Step 4 — Future Load Growth
A transformer installed today will typically remain in service for 25 to 30 years. Load rarely stays constant over that period.
- Known expansion — where a second phase of the project is already planned, include it in the calculation
- General growth allowance — 20 to 25 % is common practice where no specific expansion is identified
- Electrification trends — EV charging, heat pumps and process electrification are adding load to installations that were designed before they existed
The allowance should be a judgement, not a habit. Adding 25 % to a load that will genuinely not grow means paying for no-load losses on unused capacity for three decades.
Step 5 — Standard Ratings
Transformers are manufactured in standard kVA steps. Select the next rating above the calculated design capacity.
Worked Example — Light Industrial Facility
Connected loads:
Production machinery: 420 kW
HVAC: 95 kW
Lighting: 40 kW
Office and ancillary: 35 kW
Step 1 — Total connected load = 590 kW
Step 2 — Demand factor 0.70 → 590 × 0.70 = 413 kW
Step 3 — Power factor 0.85 → 413 / 0.85 = 486 kVA
Step 4 — Future growth 20 % → 486 × 1.20 = 583 kVA
Step 5 — Select 630 kVA
The selected unit runs at 77 % of rating at present load, leaving headroom for the anticipated growth. At full projected load it would sit at 93 % — acceptable, though at that point the site would be approaching the need for additional capacity.
Worked Example — Solar Power Plant
Sizing for generation differs from sizing for load. The transformer must handle the plant's full output, and the inverter rating rather than a diversity calculation sets the figure.
A solar plant with 20 inverters rated 100 kVA each:
Total inverter capacity = 20 × 100 = 2000 kVA
Diversity — none applied. All inverters produce simultaneously at peak irradiance.
Power factor — inverters typically operate at or near unity, but grid codes may require reactive support at 0.95 leading or lagging.
Select 2000 kVA, or 2500 kVA where reactive power capability is required by the grid code.
The Loading Question
Two figures matter and they pull in opposite directions:
The Peak Efficiency Index defines the loading at which a transformer is most efficient. See How to Calculate PEI for the method.
One Large Unit or Two Smaller?
Where the calculated capacity is substantial, splitting it across two transformers is often worth considering.
Factors That Change the Answer
- Ambient temperature — standard ratings assume a maximum ambient of 40 °C and a yearly average of 20 °C. Higher ambient requires either derating or a design specified for the site conditions.
- Altitude — above 1000 m, reduced air density lowers cooling effectiveness. Derating or a modified design applies.
- Harmonic content — non-linear loads increase winding and core heating beyond what the RMS current suggests. Installations dominated by drives and rectifiers need either a derating factor or a design that accounts for harmonic loading.
- Load profile — a transformer carrying peak load for two hours a day behaves differently from one at constant load. IEC 60076-7 provides loading guidance based on the thermal time constants of the unit.
- Motor starting — large direct-on-line motor starts draw six to eight times full load current briefly. The resulting voltage dip may govern the impedance selection rather than the kVA rating.
Common Mistakes
- Sizing on connected load without diversity — produces a transformer two or three times larger than necessary, running permanently at low load with poor operational efficiency.
- Ignoring power factor — sizing a 500 kW load as 500 kVA leaves the transformer overloaded from the first day if the actual power factor is 0.8.
- Compounding safety margins — a demand factor already conservative, plus a growth allowance, plus rounding up to the next standard rating, plus a further margin "to be safe" can double the required capacity.
- Overlooking the loss class — two transformers of identical rating can differ substantially in energy consumption over their lifetime. The rating determines what the unit can carry; the loss class determines what it costs to run.
Know the rating you need?
DATSAN manufactures oil-immersed distribution and power transformers from 25 kVA to 30 MVA in Standard, Ecodesign Tier 1 and Tier 2 loss classes. Browse the full product range or contact our engineering team with your load data for a sizing recommendation.
English (English)
Turkish (Türkçe)
French (Français)
Arabic (عربي)