IEC 60076-1 divides transformer testing into three categories. Routine tests are performed on every unit and cannot be waived. Type tests verify a design rather than an individual transformer, and are performed on one unit of each design. Special tests are carried out only when the purchaser specifies them.
Knowing which category a test falls into is what determines whether it appears in the price, whether it delays delivery, and whether a certificate from a previous project can be accepted in place of a new test.
The Three Categories
Routine Tests
Performed on every transformer before dispatch. The test report accompanying the unit records the results.
Type Tests
Performed on one transformer representing a design. Where a manufacturer has previously type tested an identical design, that certificate is normally accepted.
Special Tests
Carried out only when the purchaser requests them. Each adds cost and, in some cases, delivery time.
Reading a Test Report
The test report is the document that turns a specification into a verified fact. Four figures deserve particular attention:
- No-load loss (P₀) — compare against the guaranteed value. IEC 60076-1 permits a tolerance of +15 % on no-load losses, and +10 % on total losses.
- Load loss (Pₖ) — normally corrected to 75 °C. Confirm the reference temperature stated in the report matches the basis of the guarantee.
- Impedance voltage (Uk) — permitted tolerance is ±10 % for two-winding transformers. This value governs the fault level at the installation, so a unit at the top of the tolerance band behaves differently from one at the bottom. See Transformer Short-Circuit Current Calculation.
- Voltage ratio — tolerance is the lesser of ±0.5 % of the specified ratio, or one tenth of the impedance voltage percentage.
Factory Acceptance Testing
A Factory Acceptance Test is not a separate category of test under IEC 60076 — it is the purchaser or their representative attending while the routine tests are performed.
What it provides:
- Direct observation that the tests were carried out as reported
- Opportunity to inspect the unit before dispatch — nameplate details, accessories, paint finish, terminal arrangement
- A point at which any discrepancy can be resolved before the transformer leaves the factory
Where a FAT is required, it should be stated at the enquiry stage. It affects scheduling, since the test slot must be coordinated with the purchaser's travel.
What to Specify, and What Not To
Over-specification is common and expensive. Two examples:
Short-circuit withstand testing on a standard distribution transformer is rarely justified. The test is destructive in practice, requires an independent high-power laboratory, and adds significant cost. IEC 60076-5 permits verification by design calculation for units within defined limits, and this is accepted by most utilities.
Partial discharge measurement on a 400 V secondary distribution transformer adds little. The test earns its cost at higher voltage classes where insulation stress is closer to design limits.
Conversely, two tests are frequently omitted and should not be:
- Temperature rise test where the transformer will operate at high ambient temperature or with a non-standard cooling arrangement. The design calculation is reliable for standard conditions; it is less so outside them.
- Baseline DGA on any unit that will be monitored during service. Without a starting point, later gas readings are much harder to interpret.
Accreditation
A test report carries weight in proportion to the credibility of the laboratory that produced it. Three levels are commonly encountered:
- Manufacturer's own laboratory, not accredited — adequate for routine tests where the purchaser has confidence in the supplier
- Manufacturer's laboratory accredited to ISO/IEC 17025 — the measurement system, equipment calibration and procedures have been independently assessed
- Independent third-party laboratory — required for short-circuit withstand testing and specified by some utilities for type tests
Where a project specification calls for accredited testing, confirm that the accreditation scope actually covers the tests in question. An ISO/IEC 17025 certificate is issued for a defined list of tests, not for the laboratory as a whole.
Practical Notes
- Ask for the test report before dispatch, not on delivery. Discrepancies are far easier to resolve while the unit is still in the factory.
- Keep the test report with the transformer's maintenance file. Winding resistance, insulation resistance and DGA readings from the factory become the baseline for every later comparison.
- Where several identical units are ordered, routine tests apply to each one individually. Confirm that the report you receive corresponds to the serial number of the transformer delivered.
- Loss tolerances are one-sided. Losses may be higher than guaranteed by the permitted margin, but a unit measuring below the guaranteed figure is simply better than specified.
Need specific tests for your project?
DATSAN performs routine tests on every transformer, with type and special tests available on request. Testing is carried out to IEC 60076 and ANSI C57 in an ISO/IEC 17025 accredited laboratory. Browse the full product range or contact our engineering team to discuss your test requirements.
English (English)
Turkish (Türkçe)
French (Français)
Arabic (عربي)